Taft Hill Road Widening Project Limits Map
Taft Hill Widening Project Limits

 STATUS REPORT

Last Updated: August 2024


SCOPE OF WORK

Widening approximately 0.5 mile of roadway (Horsetooth to Harmony). Improvements include:

  • 4-lane roadway
  • center turn lane
  • right turn lanes at Horsetooth
  • curb and gutter
  • sidewalks and bicycle lanes
  • storm sewer improvements
  • intersection improvements at Harmony

PURPOSE

This project is planned due to:

  • regional/local capacity improvements
  • safety improvements
  • air quality improvements

City of Fort Collins and Larimer County partnership project

BUDGET

$9,700,000

      Grant Funding for the Project:  
      $3,834,025 Surface Transportation Block Grant (STBG)    
      $   250,000 Community Project Funding Grant (CPF)  

PROJECT STATUS

  • design engineering consultant hired (Wilson & Co.) 
  • final design is complete
  • right-of-way acquisitions in progress
  • construction expected to begin 2025

CDOT required clearances and approvals:

  • environmental - complete
  • right-of-way plans - complete
  • utility relocations - complete
  • overall design - complete

More information:  Taft Hill - Horsetooth to Harmony           
 

CONTACT

Larimer County  
Erich Purcell, Project Manager  
(970) 498-5733  
email Erich

City of Fort Collins  
Florian Fiebig, Project Manager 
ffiebig@fcgov.com