Highway 34 and Glade Road Intersection

 

STATUS REPORT

Last Updated: February 2025


SCOPE OF WORK

Install 4-direction traffic signal. Improvements include:

  • traffic signal
  • traffic cameras

PURPOSE

This project is planned due to:

  • safety improvements

BUDGET

$612,000

PROJECT STATUS

  • construction is complete
  • traffic signal is operational
  • final "punch list" items (site cleanup, seeding, etc.) to be completed

CONTACT

Devin Traff, Project Manager 
(970) 498-5731 