Highway 34 and Glade Road Intersection

 

STATUS REPORT

Last Updated: November 2024


SCOPE OF WORK

Install 4-direction traffic signal. Improvements include:

  • traffic signal
  • traffic cameras

PURPOSE

This project is planned due to:

  • safety improvements

BUDGET

$612,000

PROJECT STATUS

  • underground equipment installation complete
  • above ground equipment installation will be completed when available
  • construction expected to be complete December 2024