Bridge crossing County Road 56 North of State Highway 287

STATUS REPORT

Last Updated: November 2024

SCOPE OF WORK

Replacement of bridge. Improvements include:

  • Prefabricated aluminum plate arch bridge

PURPOSE

This project is planned due to:

  • safety improvements

BUDGET

$500,000

PROJECT STATUS

  • design engineering consultant hired (AVI PC)
  • final design is complete
  • survey complete
  • construction began September 30, 2024
  • construction expected to be complete January, 2025

CONTACT

Morgan Fay, Project Manager 
(970) 498-5739 