SCOPE OF WORK

Guardrail Installation at 3 location. Improvements include:

  • new guardrail on Pingree Hill Road (CR 69) north of State Highway 14
  • new guardrail on CR 74E east of McNey Hill
  • new guardrail on CR 74E west of CR 67A

PURPOSE

This project is planned due to:

  • safety improvements

BUDGET

$320,265

Funded in part by a Federal Highway Safety Improvement Program (HISP) Grant

PROJECT STATUS

  • design is an progress
  • environmental investigation coming soon
  • construction expected in Spring/Summer 2026