STATUS REPORT
Last Updated: November 2024
SCOPE OF WORK
Replacement of existing 10-span timber bridge on CR 45E 0.2 mile West of State Highway 287. Improvements include:
- replacement of the existing bridge
PURPOSE
This project is planned due to:
- safety improvements
BUDGET
$50,000 (design)
PROJECT STATUS
- design engineering consultant hired (AVI PC)
- design underway
- hydraulic & hydrologic investigations underway
- initial survey complete
- geotechnical survey complete
- environmental surveys underway
- construction expected in August 2025