STATUS REPORT
Last Updated: November 2024
SCOPE OF WORK
Widening and reconstruction of 2 miles of roadway along Owl Canyon Road (CR 9 to CR 13). Improvements include:
- 6 to 8 foot paved shoulders
- culvert & structure crossing replacements
- utility relocations
- subgrade stabilization
PURPOSE
This project is planned due to:
- pavement rehabilitation
- safety and shoulder widening improvements
This project phase will end just east of the south leg of CR 13
BUDGET
$10,000,000.00
$1,000,000 federal aid grant
PROJECT STATUS
- design engineering consultant hired (SEH, Inc.)
- construction (CR 9 to CR 11) expected in 2025
- construction (CR 11 to CR 13) may be phased separately
- landowner meetings in progress
- public open house will be scheduled
- CDOT required clearance and approvals:
- environmental
- right-of-way plans
- utility relocations
- overall design