STATUS REPORT
Last Updated: November 2024
SCOPE OF WORK
Paving approximately 1.21 miles of roadway along E County Road 50 (East of I-25 to CR 5) and CR 5 (Salmon Run Rd to CR 50). Improvements include:
- new asphalt roadway surface
- gravel shoulders
- grading and shaping roadside drainage
PURPOSE
This project is planned due to:
- safety improvements
- capacity improvements
BUDGET
$1,800,000
PROJECT STATUS
- site survey in progress
- soil sampling and utility locations to begin soon
- preliminary design underway
More information will be provided as it becomes available.