STATUS REPORT
Last Updated: February 2025
SCOPE OF WORK
Construct 1.3 miles of sidewalk.
- pedestrian/bicycle sidewalks
PURPOSE
This project is planned due to:
- safety improvements
- non-motorized connections
BUDGET
$1,362,500
Transportation Alternatives Program (TAP) grant
PROJECT STATUS
- design complete
- utility conflicts resolved
- environmental inspections complete and approved
- right-of-way acquisitions complete
- CDOT has approved the right-of-way package and the project in under review by CDOT Headquarters
- construction expected spring of 2025