STATUS REPORT

Last Updated:  August, 2024

SCOPE OF WORK

Widening and repaving approximately 1.2 miles of roadway (Highway 1 to CR 17). Improvements will include:

  • 2-way center turn lane
  • paved shoulders
  • asphalt overlay
  • update existing culverts and irrigation ditch crossings
  • possible turn lanes at CR 17 intersection

PURPOSE

This project is planned due to:

  • deteriorating pavement conditions
  • safety improvements
  • capacity improvements

This project is not related to the Thornton Pipeline project. Questions regarding the proposed pipeline should be directed to Larimer County Community Development, Planning Department at (970) 498-7679.

BUDGET

$3,500,000

PROJECT STATUS

  • engineering design consultant hired (JUB Engineering)
  • preliminary plans expected to be complete this year
  • topographic survey complete (King Surveying)
  • coordination with ditch company and utilities in progress
  • an open house for public comment will be scheduled once preliminary plans are complete
  • construction is expected to begin in 2026

More information:  CR 54 (Douglas Road) Safety Improvement Project