Monroe Avenue Bridge

STATUS REPORT

Last Updated: November 2024


SCOPE OF WORK

Replacement 2-span rubble arch culvert. Improvements include:

  • widen/lengthen bridge
  • creek channel grading and bank stabilization
  • 6 foot paved shoulder/bicycle lanes
  • curb/gutter/sidewalks

PURPOSE

This project is planned due to:

  • capacity improvements
  • safety improvements

BUDGET

$350,000 (design)

PROJECT STATUS

  • design engineering consultant hired (SEH, Inc.)
  • design plans in review
  • coordination with City of Loveland and utilities in progress
  • construction tentatively scheduled for September or October, 2025 and will continue through Spring, 2026

CONTACT

Morgan Fay, Project Manager 
(970) 498-5739 