STATUS REPORT
Last Updated: November 2024
SCOPE OF WORK
Replacement 2-span rubble arch culvert. Improvements include:
- widen/lengthen bridge
- creek channel grading and bank stabilization
- 6 foot paved shoulder/bicycle lanes
- curb/gutter/sidewalks
PURPOSE
This project is planned due to:
- capacity improvements
- safety improvements
BUDGET
$350,000 (design)
PROJECT STATUS
- design engineering consultant hired (SEH, Inc.)
- design plans in review
- coordination with City of Loveland and utilities in progress
- construction tentatively scheduled for September or October, 2025 and will continue through Spring, 2026